Mechanical and Electrical works, Supplied and fitted all storage and furniture, Solid and glass partitions and folding dividing walls, Ceilings and flooring, Decoration, and Refreshment area
img_gallery_20
To be completed without interrupting the use of toilets for the office block.
img_gallery_21
Amongst all standard trades this project included: Ceilings, M&E Works, partitioning, decorating, bespoke joinery and collaboration features.
img_gallery_22
Building Interiors completed a full strip out of the existing building and installed the agreed Design & Build scheme to the high standard that HH Global required.
img_gallery_23
New Furniture ranged from stunning Vitra pieces to contemporary systems furniture.
img_gallery_26
A lot of the details could not be determined until after the strip out phase and the features were uncovered. For this reason, the design process was ongoing on a week to week basis and heavily discussed and agreed with the client.
img_gallery_27
Objective; To bring staff together. Design, Plan and Fit a new break-out and gaming area to create a vibrant communal space for employees across three buildings.
img_gallery_29
We retained and refurbed where necessary and installed new bespoke joinery & high back seating pods. Other works included new flooring, lighting & decoration.